• 1,100 tonne structure raised 25 metres by 14 hydraulic jacks • Lifted at 4 metres per hour for about 6 hours • Hangar to open in October and begin activity a month later • A joint project of Iberia Maintenance (75 per cent) and the Barcelona free port authority (25 per cent)
Yesterday witnessed the most spectacular and the most delicate moment of the construction of the

Hangar’s roof before being lifted
The roof weighs 1,100 tonnes, including its structural elements weighing 850 tonnes, plus the fire extinguishing and electrical installations. To raise it 14 hydraulic jacks were used, standing on special bases at the sides and rear. They lifted the structure to a height of metres, which will be the maximum height of the working space inside the hangar, although the external height of the building will be 40 metres.
The roof was assembled over a period of five months on the floor of the hangar. It is made of 12,800 steel pipes connected by 3,000 spherical joints, the largest of them weighing 500 kg. It is supported by two lateral arches anchored to the two concrete walls and a series of metal pillars at the rear of the hangar.
The area of the roof is now 11,000 square metres, but on completion it will be increased to 13,150 square metres.
Raised in two stages
The roof was raised in two stages:
On March 19th, it was raised a few centimetres from the floor, so the following tasks could be performed:
The second stage, completed yesterday, involved:
Remaining tasks now that roof is up
A unique design
Side view of hangar model: open central doors and part of glassed-in area
The oval floor plan and the 155 square metres of glass admitting natural light in the rear make the new hangar quite unique and different from others built in
To facilitate maintenance tasks and for the ensure the comfort of employees, the hangar will have 8 moving connection boxes, or platforms that rise from the floor with connections for water, compressed air, electric power, data lines and telephone lines to be used when and where they are needed; elevated transport then allow technicians to work at any elevation throughout the building; a programmable control panel for opening and closing the 12 doors; and radiant floor heating for optimum comfort in the hangar.
Located very near the Terminal 2 building (formerly Terminal C), the hangar has an area of 13,200 square metres on a site of 24,000 square metres.
The roof was assembled on the floor over a 5-month period
In operation at the end of the year
The hangar will be officially opened in October and activity will begin a month later, after all equipment and installations have been tested. The hangar represents an investment of 24 million euros, of which
The new hangar at
An Iberia Maintenance technician inspects landing gear
Iberia Maintenance serves more than 100 airlines and aircraft manufacturers in its
|
The
|
||
|
Site |
Area |
24,000 m2 |
|
Hangar |
Oval floor |
13,200 m2 |
|
|
Maintenance area |
11,200 m2 |
|
|
Workshops/Offices with two levels |
3,600 m2 |
|
|
Internal working height |
25 m |
|
|
External height |
40 m |
|
|
Glass wall |
155 m2 |
|
Doors |
Number and weight |
12 of 40 tonnes and 300 m2 of area each |
|
Roof |
Number of spherical joints |
3,000 |
|
|
Number of steel rods |
12,800 |
|
Fire extinguishing |
Foam generators |
247 |
|
|
Water tank |
1,500,000 litres |
|
Mobile arches |
Number |
8 |
|
Elevated transport |
Bridge cranes |
4 |
|
|
Telescopic Baskets |
1 |
|
|
Trolley hoist |
1 |